Accelerated Product Development

The Challenge

Problem


• Technical difficulty: develop a new, cheaper, smaller and more efficient water heater

• Extremely long Lead Time (28 months)

• Reduction in time-to-market essential to increase sales



Root Causes


• Planning lacking any specific details and includes only the major milestones

• Plan not visible and not known by all stakeholders

• Tasks planned with a lot of safety (buffer)

• Poor integration of functions and suppliers

The Solution

• Optimized Pull Planning with buffers

• Obeya Room (Visual Project Management)

• Daily KAIZEN™ for Engineering and Testing Teams

• Last Planner with supplier integration

The Results

The project resulted in a saving of 84 man-months and a vertical production and market start-up.


time-to-market

Time-to-market

The time-to-market for the product decreased by 25%

development-costs-benefits

Development costs

Product development costs decreased by 24%



Are you interested in Kaizen Institute's consulting services?

We assist client teams in achieving great results by putting breakthrough paradigms into action.

Are you interested in Kaizen Institute's training courses?

Kaizen Institute's distinctive training program includes learning the theory and practice and gemba visits.

arrow up