Accelerated Plant Shutdown

The Challenge

opportunities-project-planning

Problem


• Summer shutdown maintenance with many inefficiencies and a lack of standards

• High manpower costs (80 external resources)

• Long duration (3 weeks)



Root Causes


• Spares/tools not ordered in advance

• Critical plan not visible

• Tasks planned with a lot of safety (buffer)

• Little time invested in task and resource planning

The Solution


mission-control-meeting-plant-shutdown

• Pull Planning with time and cost buffers

• Visual management boards for work and KPI monitoring

• Spare parts stored near machines, and tool/consumable kits prepared

• Daily cost control

The Results

The project resulted in Annual Savings of $2.5 million.


manpower-cost-reduction-benefits

Manpower cost reduction

Manpower costs reduced by 25%

shutdown-duration-benefits

Shutdown duration

Shutdown duration reduced by 10%



Are you interested in Kaizen Institute's consulting services?

We assist client teams in achieving great results by putting breakthrough paradigms into action.

Are you interested in Kaizen Institute's training courses?

Kaizen Institute's distinctive training program includes learning the theory and practice and gemba visits.

arrow up